Pengurasan Saluran di Jalan Gatot Subroto Capai 90 Persen

Channel Dredging Work on Jalan Gatot Subroto has Touched 90 Percent

Channel dredging work on Jalan Gatot Subroto, Mampang Prapatan Sub-district, South Jakarta that has been carried out since May, has now reached 90 percent. According to plan, this work will be completed in the next two weeks.

If it goes well, we estimate it to finish in the next two weeks

South Jakarta SDA Sub-agency Head, Mustajab conveyed, dredging was carried out more than 500 meters, from Satria Mandala Museum until Palm Court Apartment.

Channel on Jalan Mangga Being Normalized

"Dredging is carried out because the channel is already full of mud thus it cannot hold water optimally," he mentioned, Tuesday (8/31).

His side deployed 9 PJP personnel from Mampang Prapatan Sub-district SDA Unit to dredge the channel manually.

"They enter the channel through manhole and clean the mud as thick as 60 centimeters," he said.

By cleaning the channel, his side hopes it can hold more water thus inundation can be minimized.

"Currently, its progress has reached 90 percent. If it goes well, we estimate it to finish in the next two weeks," he informed.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye869 personTiyo Surya Sakti
  2. TransJabodetabek Expansion, a Strategic Step to Increase Public Transportation Use

    access_time26-01-2026 remove_red_eye428 personFakhrizal Fakhri
  3. South Jakarta Tackles 38 Dengue Cases to Prevent Outbreak

    access_time02-02-2026 remove_red_eye397 personTiyo Surya Sakti
  4. Jakarta Prepares OMC and 200 Excavators to Prevent Flood

    access_time26-01-2026 remove_red_eye371 personDessy Suciati
  5. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye359 personDessy Suciati
close